28th Street South - Neighborhood Complete Streets Project

  • Completion DateFebruary 11, 2025

Status

Complete


About the Project

28th-St-Project-Map.png

The Neighborhood Complete Streets program implemented improvements to the existing sidewalk, curb ramps and transit stops at three locations on 28th Street South between South Meade Street and 26th Street South.

The location received a high score and ranked highly among approximately 200 publicly nominated neighborhood street locations, using an objective criteria to sort and rank potential projects.

The improvements provide more comfortable, accessible pedestrian crossings and transit stops, that narrowed the roadway and shortened the crossing distances at three key locations in this transit corridor. The project also created an estimated net of five parking spaces.

Activity in the area includes Gunston Middle School and Community Center, the Gunston Bubble, park and playing field space, and nearby retail, in close proximity to this medium density residential neighborhood.

Project Designs

Revised Final Concept (December 2022)

Final Concept

Prior Concepts


Public Process

The project was identified through the Neighborhood Complete Streets Program process. It began with an application received from the Arlington community, which scored highly on an objective criteria matrix approved by the County Board and initiated by the Neighborhood Complete Streets Commission (NCSC) on the advice of staff. Learn more about the Neighborhood Complete Streets Process.

Design Approval

ThisNeighborhood Complete Streetsproject has completed design work and community engagement. A final concept, informed by community feedback, was approved by theNeighborhood Complete Streets Commissionat a public Funding Hearing, and subsequently approved by the Arlington County Board.

 

December 2022 Update

A revised concept design was presented to the Neighborhood Complete Streets Commission at their December 2022 meeting. Revisions were the result of staff feedback in the review process.

Winter 2022 - Concept Design Engagement

Staff developed and shared a concept plan to address safety and access challenges in the street section. Community members could share feedback using an online form. Feedback shared will be used to help refine a final design.

Staff also presented to the Pedestrian Advisory Committee on March 9, 2022.


Funding

The project was estimated to cost $880,500. The Neighborhood Complete Streets program is funded through the County’s Capital Improvement Plan (CIP).