1501 Langston Boulevard – Air & Space Force Association Site

Under Review

Location

The 1.31-acre site is located on Langston Boulevard in the North Highlands neighborhood. It is bound by Langston Boulevard and Interstate 66 to the south, N. Oak Street to the east, the Palisades Park townhouse community to the north and west, and Park Georgetown apartments to the west. A segment of the Martha Custis pedestrian and bicycle trail is located on the site’s southern border, and the Key Bridge Mariott site is located to the east. The subject site is currently developed with an 85,422-square-foot office building constructed in 1984 and expanded in 2002 (SP #361). 1501 Langston Blvd., Arlington, VA 22209  View Map

Google Map

Status

Under Review

This reports the status related to the Site Plan Review Process only (Administrative Regulation 4.1).

About the Project

1501 Langston Boulevard image for project page

SPLA25-00018

Project Description

The applicant, Taicoon Property Partners, proposes to demolish the existing office building and construct an 88-unit, eight-story residential condominium building with ground floor “institutional” space and 149 parking spaces located in the existing, to-remain underground parking garage.

Additional project details include:

  • Use Permit (UPER25-00038) for an institutional use to permit a museum to commemorate the Air & Space Force Association on the ground floor. The museum will be open to the public, operated by the developer, and will be 1,409 square feet in size. The use will have three allocated parking spaces located in the underground parking garage.
  • Density
    • 88 units (69 dwelling units per acre)
    • 220,114 square feet of residential GFA
    • 1,409 square feet of institutional GFA for a museum on the ground floor
    • Total GFA: 221,523 sq. ft. / Total FAR: 3.89
  • Building Height
    • 8 stories
    • 101.1 feet
  • Parking
    • Residential: 0.5 spaces per unit (44 spaces)
    • Institutional: 1 space per 500 sq. ft. (3 spaces)
    • Flex: 102 spaces
    • Total parking: 149 spaces
  • Zoning Ordinance Modifications Requested:
    • Density Exclusions
    • Lot Coverage
    • Residential Parking Ratio
    • Others as necessary

Application Materials

Public Process

Timeline

Milestone / Meeting

Materials

December 2025

Site Plan Acceptance

January 2026 Site Plan Review Process Kick-Off   

February 19 - March 1, 2026

Online Engagement Opportunity 

Results

Friday, March 13 Walking Tour (In-person) Walking Tour Map(PDF, 6MB)

Thursday, March 19, 2026

 

Meeting Recording

Hybrid Site Plan Review Committee (SPRC) Meeting #1 

Topics:

  • Land Use & Density
  • Site Design
  • Building Height, Form, & Architecture

Monday, May 11, 2026

 

Hybrid Site Plan Review Committee (SPRC) Meeting #2

Topics:

  • Transportation
  • Environmental Impacts
  • Open Space & Landscaping
  • Sustainability
  • Construction

September 9, 2026

Planning Commission

Public Hearing

September 19, 2026

County Board

Public Hearing

*Process timelines are subject to change as needs arise. Check back for updates.