1501 Langston Boulevard – Air & Space Force Association Site
Under Review
Location
The 1.31-acre site is located on Langston Boulevard in the North Highlands neighborhood. It is bound by Langston Boulevard and Interstate 66 to the south, N. Oak Street to the east, the Palisades Park townhouse community to the north and west, and Park Georgetown apartments to the west. A segment of the Martha Custis pedestrian and bicycle trail is located on the site’s southern border, and the Key Bridge Mariott site is located to the east. The subject site is currently developed with an 85,422-square-foot office building constructed in 1984 and expanded in 2002 (SP #361). 1501 Langston Blvd., Arlington, VA 22209 View Map
38.89960688576457, -77.07597666095367
The 1.31-acre site is located on Langston Boulevard in the North Highlands neighborhood. It is bound by Langston Boulevard and Interstate 66 to the south, N. Oak Street to the east, the Palisades Park townhouse community to the north and west, and Park Georgetown apartments to the west. A segment of the Martha Custis pedestrian and bicycle trail is located on the site’s southern border, and the Key Bridge Mariott site is located to the east. The subject site is currently developed with an 85,422-square-foot office building constructed in 1984 and expanded in 2002 (SP #361). 1501 Langston Blvd. ,
Arlington, VA 22209
The 1.31-acre site is located on Langston Boulevard in the North Highlands neighborhood. It is bound by Langston Boulevard and Interstate 66 to the south, N. Oak Street to the east, the Palisades Park townhouse community to the north and west, and Park Georgetown apartments to the west. A segment of the Martha Custis pedestrian and bicycle trail is located on the site’s southern border, and the Key Bridge Mariott site is located to the east. The subject site is currently developed with an 85,422-square-foot office building constructed in 1984 and expanded in 2002 (SP #361). 1501 Langston Blvd. ,
Arlington, VA 22209
1501 Langston Boulevard – Air & Space Force Association Site
StatusUnder Review
This reports the status related to the Site Plan Review Process only (Administrative Regulation 4.1).
About the Project

SPLA25-00018
Virtual Walking Tour - Coming Soon
Project Description
The applicant, Taicoon Property Partners, proposes to demolish the existing office building and construct an 88-unit, eight-story residential condominium building with ground floor “institutional” space and 144 parking spaces located in the existing, to-remain underground parking garage.
Additional project details include:
- Density
- 88 units (69 dwelling units per acre)
- 207,523 square feet of residential GFA
- 1,266 square feet of institutional GFA for a museum on the ground floor (0.6 FAR)
- Total GFA: 208,789 sq. ft. / Total FAR: 3.67
- Building Height
- 8 stories (under review)
- 88.5 feet
- Parking
- Residential: 1.6 spaces per unit (141 spaces)
- Institutional: 1 space per 500 sq. ft. (3 spaces)
- Total parking: 144 spaces
- Zoning Ordinance Modifications Requested:
- Density Exclusions
- Lot Coverage
- Others as necessary
Application Materials
Public Process
- This project will undergo public review via a Site Plan Review Process. Learn more.
- The SPRC Chair for this project is Sara Steinberger.
- SPRC Membership Roster (to be uploaded upon adoption).
|
Timeline
|
Milestone / Meeting
|
Materials
|
|
December 2025
|
Site Plan Acceptance
|
|
| January 2026 |
Site Plan Review Process Kick-Off |
|
|
February 19 - March 1, 2026
|
Online Engagement Opportunity
|
Results
|
| Friday, March 13 |
Walking Tour (In-person) |
Walking Tour Map(PDF, 6MB) |
|
Thursday, March 19, 2026
7 - 9 p.m.
- Meeting ID: 216 243 264 164 39
|
Hybrid Site Plan Review Committee (SPRC) Meeting #1
Topics:
- Land Use & Density
- Site Design
- Building Height, Form, & Architecture
|
|
|
TBD
|
Hybrid Site Plan Review Committee (SPRC) Meeting #2
Topics:
- Transportation
- Environmental Impacts
- Open Space & Landscaping
- Sustainability
|
|
|
TBD
|
Planning Commission
Public Hearing
|
|
|
TBD
|
County Board
Public Hearing
|
|
*Process timelines are subject to change as needs arise. Check back for updates.