1401 Wilson Boulevard
Under Review
Location
The 2.1 acre (91,614 sf) site is located at 1401 Wilson Boulevard and 1400 Key Boulevard in Rosslyn. The site is currently occupied by two 12-story office buildings constructed in 1964. The site is bordered by the Key & Nash condominiums and Turnberry Tower condominiums to the north, Hyatt Centric Arlington hotel and the unbuilt Ames Center Site Plan (SP #1) to the east, an office building to the south, and 1800 Oak apartments and an office building to the west., Arlington, VA 22209 View Map
38.89583197921165, -77.07360004225859
The 2.1 acre (91,614 sf) site is located at 1401 Wilson Boulevard and 1400 Key Boulevard in Rosslyn. The site is currently occupied by two 12-story office buildings constructed in 1964. The site is bordered by the Key & Nash condominiums and Turnberry Tower condominiums to the north, Hyatt Centric Arlington hotel and the unbuilt Ames Center Site Plan (SP #1) to the east, an office building to the south, and 1800 Oak apartments and an office building to the west. ,
Arlington, VA 22209
The 2.1 acre (91,614 sf) site is located at 1401 Wilson Boulevard and 1400 Key Boulevard in Rosslyn. The site is currently occupied by two 12-story office buildings constructed in 1964. The site is bordered by the Key & Nash condominiums and Turnberry Tower condominiums to the north, Hyatt Centric Arlington hotel and the unbuilt Ames Center Site Plan (SP #1) to the east, an office building to the south, and 1800 Oak apartments and an office building to the west. ,
Arlington, VA 22209
1401 Wilson Boulevard
StatusUnder Review
This reports the status related to the Site Plan Review Process only (Administrative Regulations 4.1).
About the Project
SPLA26-00001 (Major Site Plan Amendment)
Virtual Walking Tour
Project Description
The applicant, Monday Properties, proposes the construction of two 27-story residential towers, a shared partially below-grade parking structure, a planned grocery store, ground floor retail, and new public space contributing to the Rosslyn Sector Plan's 18th Street Corridor. The proposed density is approximately 10.0 FAR. This is a major site plan amendment to an approved site plan at the subject site, 1401 Wilson Blvd (SP #429).
Additional project details include:
- The zoning designation is “C-O Rosslyn” Mixed Use Rosslyn District
- The GLUP designation is “High” Office-Apartment-Hotel and is subject to GLUP Note 15: Rosslyn Coordinated Redevelopment District
| |
Wilson Tower
(South) |
Key Tower
(North) |
Total Site |
| Building Height |
300 ft |
300 ft |
- |
| Units |
506 units |
325 units |
831 units |
| Residential GFA |
471,610 sf |
415,622 sf |
887,232 sf |
| Planned Grocery Store GFA |
- |
17,004 sf |
17,004 sf |
| Ground Floor Retail GFA |
11,904 sf |
- |
11,904 sf |
| Residential Parking |
- |
- |
528 spaces
(0.63 sp/unit) |
| Residential Visitor Parking |
- |
- |
16 spaces |
| Retail Parking |
- |
- |
55 spaces |
| Loading Spaces |
2 spaces |
4 spaces |
6 spaces
(3 residential, 3 retail) |
Proposed modifications for:
- Additional density
- Density exclusions
- Reduced residential ratio
- Increased compact parking ratio (35%)
- Reduced residential loading spaces
Applicant Materials
Accepted Plan Sets [PDFs]
Public Process
| Timeline |
Milestone / Meeting |
Materials |
| January 29, 2026 |
Site Plan Acceptance |
|
| March 19 - 29, 2026 |
Online Engagement Opportunity
Focused on the following topics:
- Land Use and Density
- Site Design and Layout
- Building Height/Form/Architecture
- Transportation
- Parking and Loading
- Open Space and Landscaping
- Green Building and Sustainability
|
|
|
March 27, 2026
12:00 p.m. to 1:00 p.m.
In-person only
|
In-person Walking Tour
Meeting Location: Corner of Wilson Boulevard and North Oak Street
|
|
|
April 27, 2026
|
Hybrid Site Plan Review Committee (SPRC) Meeting #1 Agenda Topics: TBD
|
|
|
TBD
|
Hybrid Site Plan Review Committee (SPRC) Meeting #2 Agenda Topics: TBD
|
|
|
TBD
|
Planning Commission Public Hearing
|
|
|
TBD
|
County Board Public Hearing |
|
*Process timelines are subject to change as needs arise. Check back for updates.