2001 S. Clark St. (2001 S. Bell St.) – Crystal Plaza 1

Location

2001 S. Clark St., Arlington, VA 22201  View Map

Google Map

Status

Approved

Overview map of site area

This project was approved by the County Board on May 15, 2021.

Check building permit status.

About the Project

The applicant, JBG Smith, proposes redevelopment of an existing office building into two (2) residential towers with ground floor retail. Learn more details about the project:

Additional project details include:

  • Rezoning (Z-2619-19-1): to rezone the area of the new site plan for Crystal Plaza 1 from “M-2,” Service Industrial and “C-O”, Mixed Use District to “C-O Crystal City”, Mixed Use Crystal City district.
  • Crystal City Block Plan: Block Plan for “Block M” as required by the proposed rezoning above.
  • Phased Development Site Plan (PDSP) Amendment (SP #454): an amendment to the existing “Crystal City PDSP” (SP #454) to incorporate the new site plan into the PDSP.
  • Site Plan Amendment (SP #11): site plan amendment to remove 104,404 sq. ft. from the existing SP #11.
  • New Site Plan (#458): a new site plan and development proposal to demolish the existing Crystal Plaza 1 (2001 S. Clark Street) and construct two (2) new multifamily residential buildings with ground floor retail, totaling approximately 6.9 FAR and including:
    • Site area of 104,404 sq. ft. (2.396 acres)
    • “West Tower” (2000 S. Bell Street)
      • 338 dwelling units (du)
      • 12,053 sq. ft. of retail
      • 250 feet in height
    • “East Tower” (2001 S. Bell Street)
      • 420 du
      • 10,006 sq. ft. of retail
      • 200 feet in height
    • Underground parking structure (302 total spaces)
      • 0.32 spaces per du
      • 17% compact spaces
    • Replacement of existing Underground pedestrian concourse segment
    • New extension of South Bell Street, connecting to South Clark Street; and a new alley south of the proposed East Tower
    • New pedestrian plaza (aka “pedestrian passageway” or “pedestrian connection”) along the east side of the proposed East Tower

Applicant Materials

August 2020

November 2020

February 2021 – Revised Plans

March 2021

April 2021 – Planning Commission Resubmission

Public Process

  • This project will undergo public review via a virtual Site Plan Review Process. Learn more.
  • The SPRC Chair for the site plan review process is: Daniel Weir, daniel.a.weir@gmail.com
Timeline Milestone / Meeting Materials
August 2020 Site Plan Acceptance
August 2020 Site Plan Review Process Kick-off
July 27 – August 3, 2020 Online Engagement Opportunity

 

Review Focus: Crystal City Block Plan - Long Range Planning Committee (LRPC) review of Block M

September 10, 2020

 

View meeting recording

Virtual Long Range Planning Committee (LRPC) Meeting

 

Review Focus: Crystal City Block Plan M - Block Plan Review of 2000/2001 S. Bell St. and 223 23rdSt/2250 Crystal Drive site plan applications

October 19, 2020

 

View meeting recording

Virtual Long Range Planning Committee (LRPC) Meeting

 

Review Focus: Crystal City Block Plan M - Block Plan Review of 2000/2001 S. Bell St. and 223 23rdSt/2250 Crystal Drive site plan applications

December 28, 2020 – January 11, 2021 Online Engagement Opportunity

 

Review Focus: site layout, building massing, architecture, underground, open space/landscaping, streetscapes, transportation, PDSP and community benefits, and other topics

February 18, 2021

 

View meeting recording

Virtual Site Plan Review Committee (SPRC) Meeting

 

Review Focus: Building Design/Architecture, Open Space, The Underground

March 18, 2021

 

View meeting recording

Virtual Site Plan Review Committee (SPRC) Meeting

 

Review Focus: Project updates, Transportation, PDSP/Community Benefits

April 12, 2021

 

View meeting recording

Virtual SPRC/LRPC Meeting

 

Review Focus: Wrap-Up

April 29, 2021 Transportation Commission Meeting
May 3, 2021 Planning Commission Meeting

 

Public Hearing

May 15, 2021 County Board Meeting

 

Public Hearing

*Process timelines are subject to change as needs arise. Check back for updates.