1901 & 1911 Fort Myer Drive - One Rosslyn
Approved
Location
Located at 1901 and 1911 Fort Myer Drive, this 2.3-acre Rosslyn site is comprised of three (3) parcels. The site is bounded by Langston Boulevard and Gateway Park to the north, North Moore Street to the east, 19th Street North to the south, and Fort Myer Drive to the west., Arlington, VA 22209 View Map
38.89786889568477, -77.07220171534281
Located at 1901 and 1911 Fort Myer Drive, this 2.3-acre Rosslyn site is comprised of three (3) parcels. The site is bounded by Langston Boulevard and Gateway Park to the north, North Moore Street to the east, 19th Street North to the south, and Fort Myer Drive to the west. ,
Arlington, VA 22209
Located at 1901 and 1911 Fort Myer Drive, this 2.3-acre Rosslyn site is comprised of three (3) parcels. The site is bounded by Langston Boulevard and Gateway Park to the north, North Moore Street to the east, 19th Street North to the south, and Fort Myer Drive to the west. ,
Arlington, VA 22209
1901 & 1911 Fort Myer Drive - One Rosslyn
StatusApproved
This project was approved by the County Board on July 19, 2025.
This reports the status related to the Site Plan Review Process only (Administrative Regulation 4.1).
About the Project

Virtual Walking Tour
Virtual Walking Tour
Project Description
The applicant, Penzance, proposes a rezoning, Phased Development Site Plan (PDSP) Amendment and a Major Site Plan Amendment to SP #419 that would terminate the previously approved, but unbuilt, PDSP and final site plan and replace it with a new redevelopment program. The new proposal includes demolishing the existing office buildings and developing three (3) residential towers above a mixed-use podium, with retail and structured parking. Additional details include:
- 9.92 FAR total density
- 845 total dwelling units (957,306 square feet)
- 14,584 square feet of ground floor retail
- 0.65 parking spaces per dwelling unit; 6 retail parking spaces
- Residential Towers:
- Northeast (condo): 73 units; 23 stories
- Northwest: 311 units; 27 stories
- South: 461 units; 29 stories
- Sustainability: LEED Gold v4, Energy Star appliances and fixtures, Water Sense plumbing fixtures, energy cost savings over Ashrae 90.1 2010: ≥ 20%, and EV charging: minimum 2% EV installed spaces (project will not participate in the GBIP)
- Zoning Modifications Requested: additional density, reduced parking, density exclusions
*Please note that the above description and statistics are subject to change throughout the public review process
Application Materials
Accepted Plan Sets [PDFs]
Public Process
|
Timeline
|
Milestone / Meeting
|
Materials
|
|
January 2025
|
Site Plan Acceptance
|
- See "Application Materials" above.
|
| February 2025 |
Site Plan Review Process Kick-Off |
|
|
February 20 - March 3, 2025
|
Online Engagement Opportunity
Review focus:
- Land Use and Density
- Building Form and Height
- Architecture
- Transportation
- Landscaping, Biophilia, and Sustainability
- Community Benefits and Other Topics
|
Results:
|
|
March 27, 2025
7 - 9 PM
View meeting minutes(PDF, 132KB)
View meeting recording
|
Site Plan Review Committee (SPRC) Meeting #1 (Hybrid)
|
|
|
May 1, 2025
7 - 9 PM
View meeting minutes(PDF, 132KB)
View meeting recording
|
SPRC Meeting #2 (Hybrid)
|
|
| June 30, 2025 |
Transportation Commission
Public Hearing
|
|
|
July 9, 2025
|
Planning Commission
Public Hearing
|
|
| July 10, 2025 |
Housing Commission
Public Hearing
|
|
|
July 19, 2025
|
County Board
Public Hearing
|
|
*Process timelines are subject to change as needs arise. Check back for updates.