Sycamore St and Langston Blvd, View Map
Sycamore St and Langston Blvd ,
Project Background
This project will install new stormwater pipes to provide more capacity at the intersection of Langston Blvd and N. Sycamore St. The project will increase stormwater system capacity by installing an additional 76”x48” elliptical concrete pipe and two new stormwater structures.
Schedule
The initial construction contract had to be canceled and the construction contract will have to be re-bid. Construction is estimated to start in spring, 2027. Construction will last 6 months.
Project Plans
Project Diagram(PDF, 520KB)
Engagement
Project Contacts
Project Manager
Mohammad Yazdi
Communications Manager
Aileen Winquist