Gulf Branch Outfall Repairs

Construction

Status

Construction

Gulf Branch Outfall Repair - N Peary - Endwall 1

The outfalls at N Peary and N Nelson Street to Gulf Branch are actively eroding and undermining storm drain infrastructure.  

Project goals include:

  • Create a stable outfall
  • Maintain the storm infrastructure, repair erosion
  • Remove invasive plants, add native plants
  • Minimize impacts to the stream corridor

N Peary/Piedmont Street Outfall Repair 

The N Peary Outfall Repair Project will create a stable outfall and channel, repair stormwater pipes and structures, remove invasive bamboo, and plant native plants and trees. Construction starts in early 2027 and will last approximately 6-9 months. Thank you to the neighbors who have engaged with and supported this project. 

There will be trail closures during construction. Please prioritize safety by staying out of construction fencing.

Construction is expected to last 6-9 months, including: 

  • Site preparations, bamboo removal and creating the construction path, 
  • Installing the new stormwater concrete pipe and endwall, 
  • Adding stone structures to stabilize the channel and regrading the banks, 
  • A robust, diverse replanting with native trees, shrubs and plants.

To receive project email updates, please contact Lily Whitesell at LWhitesell@arlingtonva.us

Project Background: The outfall behind N Peary St and N Piedmont St leads to a small tributary of Gulf Branch. The endwall of the stormwater pipe has fallen off into the stream channel and there is a large area with invasive bamboo and steep banks. Additional site-specific project considerations include maintaining the pedestrian bridge, feasible access paths, protecting high-value habitat, and coordinating the approach with neighbors.

 

Date Location and Description Meeting Materials

Fall 2026

Pre-Construction Engagement Signage posted along trails (see above), Neighbor and civic association notices

Fall 2025 - Winter 2026

Final Design Engagement  Presentation(PDF, 5MB)
Summer 2025 Concept Design Engagement Presentation(PDF, 6MB)
2023 - Early 2025

Initial contact with immediate neighbors



 

N Nelson Street Outfall Repair

This outfall at N Nelson Street leads to another small tributary of Gulf Branch. The endwall and concrete pad have been undermined and there is extensive erosion underneath. The flow of water has created a small hole in the concrete pad and is dripping through to the area below. There is also additional erosion upslope of the outfall. The N Nelson Outfall Repair project is currently in feasibility analysis and pre-concept design.

Date Location and Description Meeting Materials
Summer 2026 Access alternatives analysis, neighbor outreach Presentation(PDF, 14MB)
2025-2026

Initial contact with immediate neighbor during information gathering

Fall 2025 Slide Deck(PDF, 5MB)