Chesapeake Bay Preservation Ordinance Amendments
Why was the ordinance updated?
Resource Protection Area, or RPA, includes streams, rivers, and other water bodies and the environmentally sensitive lands within 100 feet of these water resources. The Virginia General Assembly passed a bill to amend the Chesapeake Bay Act to further conserve trees in RPA, require buffer replanting with trees, and to require a resilience assessment for development in resource protection areas. Arlington updated our Chesapeake Bay Preservation Ordinance to include these amendments, which went into effect September 1, 2025.
What were the changes made to the ordinance?
The amendments to the ordinance focus on tree protection in the RPA and climate change impacts for development in the RPA.
Tree Protection
The tree amendments emphasize protection of mature trees (overstory trees greater than 12 inches and understory trees greater than 4 inches) during development County-wide. The tree amendments also update guidance for tree replacement and buffer restoration in the RPA and clarify requirements for removing dead trees and noxious vegetation from the RPA. Arlington was already implementing many of these requirements as a matter of policy, but the amendments will codify them and strengthen the language as part of the ordinance.
Climate Change Resilience
The climate change amendment requires an assessment of flooding, sea level rise, and storm surge for any planned development within resource protection areas to determine the potential impacts from climate change. This amendment only applies to some RPA properties, and the County has created an interactive map or a PDF map(PDF, 4MB) to determine if your property is affected. The Water Quality Impact Assessment Form was updated to include a section for the resilience assessment.
Brief Overview of Ordinance Amendments
Schedule
The Arlington County Board adopted the updated ordinance on June 14, 2025 and the new requirements went into effect on September 1, 2025.
Engagement
View the engagement activities for the updates to the Chesapeake Bay Preservation Ordinance.
| Date |
Event |
Materials |
| February, 2025 |
Letter to property owners |
|
| February, 2025 |
|
Informational Video |
| March 20, 2025. 7 PM |
Virtual public meeting |
Meeting presentation(PDF, 4MB)
Meeting Video
|
| March 24, 7 PM |
Planning Commission Information Item |
Meeting Presentation(PDF, 5MB) |
| March 27, 7 PM |
Forestry and Natural Resource Commission |
Meeting Presentation(PPTX, 20MB) |
| April 8, 7 PM |
Parks and Recreation Commission |
|
| April 10, 2 PM |
Arlington County Contractor's Meeting |
Presentation(PDF, 2MB) |
| To be scheduled |
Chesapeake Bay Ordinance Review Commission Briefing
|
|
| May 10, 2025 |
Request to Advertise County Board meeting |
Meeting agenda
Board report
Revised ordinance
|
| June 14, 2025 |
County Board Consideration of Adoption of Revised Ordinance |
Meeting agenda
Board report
Ordinance Amendments
Climate/Resiliency Map
|