Columbia Pike: Segment D

Location

Columbia Pike between South Garfield Street and South Courthouse Road., Arlington, VA 22204

Status

Construction

All wet and dry utilities have been buried. Road surface, sidewalk and signal work was completed in December of 2025. Crews will complete quality assurance and landscaping work in early 2026.

Segment-D-Widget-revised-with-Cleveland.jpg

Project Progress - February 2026

Road, sidewalk and signal work are complete as of late 2025. Crews will conduct remaining quality assurance, small tasks and landscaping work in early 2026.

Sidewalk Work

Throughout the month of January, crews will be conducting sidewalk quality assurance and repair work between South Garfield Street and South Courthouse Road.

Expect short term lane closures during work hours to allow crews to access sidewalks safely. In cases where crews are working on the full width of a sidewalk, look out for detour signs to guide your path around the work site.

Work Zone Map

Bus Stop Relocations

Bus stop temporary relocations:

  • South Walter Reed Drive westbound: Relocated to South Highland Street
  • South Barton Street eastbound: Relocated 100 west in front of Celtic House
  • South Barton Street westbound: Relocated 200 east in front of Starbucks
  • South Courthouse Road eastbound: Relocated across South Courthouse Road in front of Dorchester Apartments.
  • South Courthouse Road westbound: Relocated across South Courthouse Road to South Veitch Street

Sign up for ART Alerts to receive bus stop relocation notices.

 


About the Project

This work is part of the Columbia Pike Multimodal project to make Columbia Pike a safer, more accessible route for all users. Arlington is transforming this main thoroughfare into a complete street that balances all modes of travel and supports high-quality, high-frequency transit service.

Before the project could could implement street level improvements, the project team performed utility work to below the roadway to replace aging and leak-prone water and sewer pipes.

Streetscape improvements include:

  • Sidewalk upgrades, including widening where space is available, and leveling
  • New streetlights
  • Upgraded traffic signals
  • Street trees

Segment D Rendering


Public Process

During the planning phase with this project, staff met with adjacent property owners civic associations to discuss the Columbia Pike Multimodal Project and provide construction updates. Outreach will continue as the project moves forward.