Donaldson Run Headwaters Outfall Repair
Location
2451 Wakefield Court, 22207 View Map
38.902450, -77.123113
2451 Wakefield Court ,
22207
2451 Wakefield Court ,
22207
StatusConstruction
Background
This project will repair a failing storm sewer outfall between 24th Road North and the Analostan Homeowners Association Property which flows into Donaldson Run. The project will also stabilize the eroded stream channel below the outfall feet to a point that connects to a previously constructed stream restoration project. A section of storm sewer pipe was also previously re-aligned as part of the project. The stream stabilization will include the installation of step pools to slow the energy of the stream flow and rock walls to protect the stream channel.
Construction Schedule
Some tree removal will take place starting the first week of March, 2023. Construction is expected to begin in April/May 2023. The construction time frame is 9 months. Construction access will be from 25th St North and the Missionhurst property.
Construction Updates
June 2023
The County has issued the notice to proceed to the contractor. During the week of June 5, the contractor will be staking out the limits of disturbance for the project. During the week of June 12, the contractor will be installing erosion and sediment controls around the site.
Project plans
Part 1 - Includes existing conditions, tree inventory, erosion and sediment control plans, pollution prevention plans, plan and profile(PDF, 32MB)
Part 2 - Includes cross sections, stormwater computations, water quality impact assessment(PDF, 9MB)
Planting Plan
28 trees will be removed for the project and 630 trees, 188 shrubs, and live stakes will be planted. View the landscape plan(PDF, 4MB) and the plant list(PDF, 2MB) for the project.
Project Engagement
This project is a consult level engagement with the property owners adjacent to the project and communicate level engagement with the surrounding neighborhood.
Date |
Meeting |
Meeting Materials |
Various dates |
Meetings with property owners bordering the project |
|
April, 2017 |
Meeting with Analostan HOA |
|
March 18. 2023 |
Board Report |
Construction contract was approved by County Board (Item #22) |
March 28, 2023, 7 PM |
Informational Meeting |
Meeting presentation(PDF, 10MB)
Meeting video
|