June 2023
The County has issued the notice to proceed to the contractor. In June, the contractor has staked out the limits of disturbance for the project and started installing erosion and sediment controls around the site. During the week of June 20th, the contractor will be doing some tree removal and installing the construction entrance.
July 2023
The contractor has installed the erosion and sediment controls and is working on installing an access route to the stream and outfall.
August, 2023
The contractor has installed an access pathway made of stones along the stream. The contractor is working on installing a new end wall over the stormwater pipe and installing fill behind the end wall. When the end wall is complete, the contractor will begin work on stabilizing the stream banks.
September, 2023
The contractor completed installation of the end wall over the stormwater pipe. The contractor has started construction on the stone wall along the stream.
October, 2023
The contractor is working on installing in stream rock structures and rock vanes and continuing to build the rock wall along the stream. The contractor replaced a section of sanitary sewer pipe under the stream.
November, 2023
The contractor is encasing the new sanitary sewer pipe in concrete, and continuing to install stream rock structures, rock vanes and the rock wall along the stream.