Demolition and Microforest 6415 N. 24th St

The home at this property was damaged by flooding and County acquired the property through a voluntary property acquisition.  The home will be removed and trees will be planted on the property.

Phase 1 - Removal of the house

 The project schedule is approximately 8-12 weeks. The schedule may be adjusted because of weather delays or material supply delays. 

  • Week of June 20, 2022 – Contractor begins site preparation, installs erosion and sediment controls, installs fencing around site, mark-out utilities
  • July 11, 2022 – Demolition of the home and shed is scheduled 
  • Week of July 18, 2022 – Site restoration, backfilling site, placing seed and straw on disturbed soil areas
  • Beginning of September – Sanitary sewer renovation
  • Late September or early October – completion of fencing
  • Erosion and sediment controls (black plastic silt fence) will remain in place at the site until later in the summer when the grass is established.

The existing fence at the site will be re-used to enclose the property.  Parking along the right of way of property # 6415 will not be allowed during construction.  The working hours within Arlington County are: Monday thru Friday 8:00 am to 4:00 pm.  The County will contact residents if a change to the working hours is needed.  Work is not permitted on holidays.

Phase 2 - Tree planting.  Schedule TBD

Project Engagement

Meeting Date      Meeting Type  Meeting Materials 
 June, 2021  Neighborhood meeting   
 April, 2022  Neighborhood meeting  
 June, 2022  Pre-construction meeting  Presentation(PDF, 6MB)  

 

 

Location

6415 N. 24th St. Arlington, VA,    View Map

Google Map