The road bridge improvements were completed in summer of 2022, and the parallel pedestrian and bike bridge was completed in the fall of 2024.
The bridge has been installed and is open for the community to use.
About the Project
This project upgraded and brought the road bridge over Four Mile Run into a state of good repair, added a pedestrian and bicycle bridge to the west of the existing bridge, and implemented improvements to the area surrounding the intersection of Shirlington Road and South Arlington Mill Drive.
Video: Pedestrian bridge installation (August 2024)
Bridge maintenance work on the surface of the Shirlington Road Bridge was completed in September of 2022.
This work accomplished the following project goals:
Arlington Mill Drive and Shirlington Road Crosswalk Improvements
Pedestrian Crossing Improvements Near the Four Mile Run Trail/27th Street S
Crews completing final maintenance tasks on the Shirlington Road Bridge surface, summer 2022.
The project team engaged with the local community during the planning phase of the project.
To provide a project update, including how community feedback helped refine the advanced concept, the project team hosted a virtual meeting and question and answer session. For those unable to attend, the meeting materials are included below.
Community feedback was collected online between January and February of 2021.
To help the community learn more about the project, ask questions and share feedback, the project team hosted an online open house. For those unable to attend, the meeting materials are included below.
Community feedback was collected online between March and April of 2020.
This project is fully funded with a combination of State and County funds.
Pedestrian Bridge Abutment B Construction - April 2024
Pedestrian Bridge Abutment A Construction - April 2024
Completed Shirlington Road Bridge - September 2022
Pedestrian Improvements
View of Shirlington Road Bridge Preconstruction
Shirlington Road Bridge Preconstruction
Shirlington Road Pedestrian Bridge Frame - View from S. Arlington Mill Dr. - June 2024
Shirlington Road Pedestrian Bridge - October 2024
Project Manager Rene Harris 703-228-3809