Crystal City Metro Station Second Entrance

Location

In Crystal City on the northwest corner of Crystal Drive and 18th Street South, Arlington, VA 22202  View Map

Google Map

Status

In Design

In July 2020, the County Board approved an interim agreement with a JBG SMITH subsidiary, JBGS/TRS, LLC, for development of 30 percent design documents for the second entrance at the Crystal City Metrorail Station. Under the agreement the County will pay JBGS/TRS $3.57 million for this effort. The County Board held a public hearing on the interim agreement at its June 13, 2020, meeting.

The engineering and design process kicked off in September 2020, and the 30% design phase is anticipated to be complete in November 2021. Key elements of this phase of the project include topographical survey, environmental analysis, preliminary station design, and community stakeholder coordination.

About the Project

The Crystal City Metrorail Station is one of the more highly used stations in Arlington County. The existing entrance is reaching capacity during peak periods and has limited emergency egress. The existing street-level elevator access is slow, inconveniently located and lacks redundancy.

With redevelopment underway in Crystal City, overall trip-making will increase and transit will need to capture a substantial majority of that increase, which will overburden the existing station entrance. In addition, large volumes of passengers transfer between Metrorail and Virginia Railway Express (VRE), but the transfer route is long, circuitous and has accessibility barriers.

The access improvement plan for the Crystal City Metrorail station includes a new entrance near Crystal Drive, at the east end of the station, to provide easier access from Crystal Drive, the VRE station and the Metroway transit station at Crystal Drive and 18th Street South. In addition, the access improvement plan includes elevator upgrades to improve compliance with the Americans with Disabilities Act (ADA) and provide more conveniently located elevator access.

The new east entrance will include elevators, escalators and/or stairs, a fare payment area with fare vending machines, a kiosk, and an underground passageway and mezzanine to the existing train platform. The new entrance will provide additional egress during emergency situations.

WMATA will own and operate the new east entrance as part of the Metrorail system.

DES Crystal City Metro 2nd Entrance map

Map of proposed second entrance location 

Project goals
  • Create a multimodal hub – improve the ability to transfer among Metrorail, Metroway, VRE, ART, and Metrobus services and improve pedestrian and bicycle connections
  • Shorten commutes – increase connections to employment centers
  • Give people space – relieve congested conditions at the current Metro station entrance and on the station platform
  • Meet accessibility needs – provide direct access for customers with mobility challenges to areas east of the station
Plan for a second entrance

Project justification and planning go back many years. Arlington County’s 2010 Crystal City Sector Plan identified access improvements needed at the Crystal City Metrorail Station. In 2014, the County and WMATA identified three alternative locations in the vicinity of Crystal Drive and 18th Street South for the new east entrance. WMATA finished a report detailing these alternatives in February 2014:

In 2016, Arlington County included the project in its Transit Development Plan and Capital Improvement Plan.

WMATA evaluated the alternative locations, conducted additional engineering analysis, and obtained input from the County and adjacent property owners to finalize the location of the second entrance. WMATA finished a report detailing the conceptual design for the second entrance in November 2019:

Public Process

Washington Metropolitan Area Transit Authority (WMATA) Public Hearing - July 2021

WMATA, supported by the project team, held a public hearing on the proposed new entrance to Crystal City Metrorail Station on July 13, 2021.

Project Q&A Session - March 2021

The project team held a live virtual question and answer session on March 31, 2021. Staff answered questions about the design process and environmental review activities.

Project Update - February 2021

This video provides an update on work to advance the project design:

Previous Outreach

The public has helped shape this project for more than a decade, as plans for a second entrance were first included in the County’s 2010 Crystal City Sector Plan. Past public feedback has focused on accessibility, integration with future development, and intermodal connections. Comments suggested to:

  • Include elevators, escalators, and stairs
  • Locate entrance conveniently to the transitway and VRE
  • Consider pedestrian safety crossing Crystal Drive
  • Improve ADA access
  • Minimize construction disruptions

Many of these features have been incorporated into project plans, and other comments will be considered as they need to be addressed (e.g., construction phase).

Public input has been reflected in the following plans and programs:

  • Crystal City Sector Plan (2010): Engaged the public and stakeholders through more than 30 task force meetings, two walking tours, periodic community forums, a week-long charrette, and additional stakeholder meetings.
  • Crystal City Station Access and Second Entrance Study (2014): Recommended the selected site through an alternatives assessment. Engagement activities included two public meetings in 2012 and two sessions at VRE Passenger Day and Crystal City Day.
  • Arlington Transit Development Plan (2016): Included the project as part of the County's Capital Improvement Plan. The update process included four workshops, six events on draft recommendations, and multiple informational meetings presenting final recommendations. County staff also attended more than a dozen community meetings to share engagement opportunities and explain the update process.
  • Capital Improvement Plan Updates (2016–2020): Discussed as part of four biennial CIP processes, including the most recent FY 2021 CIP adopted in July 2020. In 2020, the CIP was changed to a 1-year timeframe to accommodate uncertainties caused by COVID-19.
  • County Staff Presentations (2018): Presented project scope at an open house in March 2018 and to the Transit Advisory Committee on July 21, 2020.
  • Crystal Square Development Review (2018): County Board approved new retail development at the northwest corner of Crystal Drive and 18th Street South, considering incorporation of the Metrorail east entrance on the site. The redevelopment underwent a one-year public review process that included Site Plan Review Committee meetings, Long Range Planning Committee meetings, public hearings before the Transportation and Planning commissions, and an online survey.

Funding

The County's FY 2019-2028 Capital Improvement Plan includes $90.8 million for this project. Anticipated funding sources include state grants, regional funds, and local commercial real estate tax revenues dedicated to transportation. In 2018 the Northern Virginia Transportation Authority approved $5 million for preliminary engineering.