23rd Street South Realignment

Location

23rd Street South between South Eads Street and Crystal Drive, Arlington, VA 22202  View Map

Google Map

Status

Construction

Before and after aerial rendering of the 23rd Street South realignment

Construction Update – September 2021

The contractor is working periodically, mostly on electrical items, but construction has paused as they coordinate with the County and Dominion to address issues related to a new traffic signal foundation and removal of a signal pole. Once the signal pole is removed, the contractor will move forward with completing the sidewalks and paving the project area.

 

Here's what to expect during Phase 1 construction:

  • Work hours will be 7 am to 6 pm, Monday through Friday
  • Lane closures will be limited to non-rush hours (between 9 am and 4 pm) with normal operations at all other times.
  • Temporary sidewalk closures will be required. When necessary, detours will be marked directing pedestrians, bicyclists and other traffic safely around the work zone.

About the Project

Phase 1 is between Route 1 and South Eads Street. This phase will widen the sidewalk and retail parking areas on the south side of 23rd Street. Lane widths will be reduced, but the number of travel lanes will remain the same as today.

On April 25, 2020, the County Board approved a $1.33 million contract with Ardent Company LLC for Phase 1. Construction activities began in September 2020, with completion anticipated in spring 2022.

Phase 2 is from Crystal Drive to Route 1, including the intersection at Route 1. This phase will be triggered by redevelopment along the north portion of 23rd Street. It will realign the roadway to eliminate the wide median island so the building pad sites on the north portion of 23rd Street can be built in accordance with the Crystal City Sector Plan.

Public Process

In spring 2018, County staff briefed the following commissions and civic associations on the project's status and removal of the pedestrian tunnel - presentation:

  • May 9, 2018 - Aurora Highlands Civic Association
  • May 15, 2018 - Disability Advisory Commission
  • May 31, 2018 - Transportation Commission
  • June 13, 2018 - Pedestrian Advisory Committee
  • June 14, 2018 - Crystal City Citizen Review Council (CCCRC)

In summer 2018, staff solicited feedback regarding the demolition and removal of the tunnel underneath Route 1. Many members of the community agreed that the tunnel should be removed due to safety issues and the facility's lack of accessibility. The 23rd Street pedestrian tunnel was closed permanently on Sept. 3, 2019, and the tunnel’s above-ground structures were deconstructed in fall 2019.

In summer 2020, staff met with adjacent business owners to coordinate construction impacts and minimize disruption.

Funding

Phase 1 is primarily funded by a regional grant from the Northern Virginia Transportation Authority.