Sept. 2026 Update:
- Tennis court light poles removed and asphalt milling complete.
- Underground stormwater utilities installation in progress.
- Restroom building materials received and on site. Foundation work and underground utilities for the building are in progress.
- Light pole foundation and electrical conduit installation in progress.
- Sanitary sewer line and waterline installed on site and on N Manchester Street. N Manchester asphalting and striping completed by DES.
- Installation of retaining walls in progress.
- Site grading is in progress.
Key Project Details and Impacts:
During construction the tennis courts, parking lot, restroom/picnic shelter, and a small section of the Four Mile Run Trail will be fenced off and closed to the public. Four Mile Run Trail users can use the adjacent W&OD Trail to avoid the small, closed trail segment before returning to Four Mile Run Trail. See the map at the bottom of this webpage for detour information.
Other key features at Bluemont Park, including the baseball diamond, soccer field, and playground, will remain open to the public. When using these facilities we recommend parking on N Manchester St, at the southern parking lot near the park's playground, or appropriate street parking in the surrounding neighborhood. Please do not park at Ashlawn Elementary School during school hours.
You can find information on other tennis court locations and availability on the County's tennis court site.