Crystal City to Reagan National Airport Multimodal Connection (CC2DCA)

This project explores the possibility of providing a context-sensitive multimodal connection between Crystal City and Ronald Reagan Washington National Airport (DCA) for use by people walking, biking, and using micromobility devices. The study includes environmental reviews required by the federal NEPA review process.

The CC2DCA connection could provide residents, visitors, and business travelers of all ages and abilities with a safe and convenient way to reach the airport from Crystal City. Not only could the project provide pedestrian and bicycle access to a national air travel hub, it could also potentially create and enhance multimodal connections among the airport, the relocated Virginia Railway Express (VRE) commuter rail station, and the multi-use Mount Vernon Trail.

Location

The potential connection will link Crystal City to National Airport. The specific location of the connection is yet to be determined.

CC2DCA study area map

Map of study area(JPG, 1MB) (full size)

Status

National Environmental Policy Act (NEPA) efforts for the CC2DCA connection began in Spring 2022. Initial activities included data collection, agency coordination and public outreach which aided in the development of the Purpose and Need statement for the study. Currently, the study is in the process of evaluating a range of alternatives for a potential connection. 

To receive updates, sign up for the Crystal City-Pentagon City Transportation Update email on the right side of this page. 

What to expect during the environmental review process

CC2DCA would use federal funds and could impact federal lands. Therefore, it is subject to NEPA and the County must develop alternatives and conduct an environmental analysis before identifying a preferred design concept. We anticipate this process will take approximately three years to complete.

This work will be done in collaboration with the Virginia Department of Transportation (VDOT) and other regional, state and federal agency partners. The potential environmental impacts of the alternatives will be evaluated in a NEPA document. This document is now anticipated to be an Environmental Assessment (EA) which would be published in late summer or early fall 2023. The study also will advance the production of required documentation and approvals by appropriate federal agencies.

A preferred alternative, including a specific type of facility and alignment, will be identified in the EA, which will also list environmental commitments to avoid, minimize, or mitigate adverse impacts on the environment from the project. After the NEPA process is complete, all necessary federal permits and authorizations will be obtained.

Arlington County will further advance the design of the selected connection in preparation for the next phase of the project (final design and construction). This work will be completed under a different contract and is not part of the study. 

Public Process

Public involvement is pivotal to the NEPA process; opportunities to engage with the study will be provided throughout its development. Given the importance of this project, the County has developed a comprehensive public participation plan in accordance with NEPA requirements and consistent with the County’s Six Step Public Engagement Guide for Capital Projects.

Fall 2022 Engagement and Community Outreach

In November 2021, the project team kicked off the 3rd public engagement opportunity for the CC2DCA Study, covering the process from initial concept designs to a recommended preferred alternative. This public engagement window is open from October 4, 2022 to November 6, 2022.

You can share your feedback in one of three ways:

Online Feedback Form

The online feedback form guides participants through a high-level overview of the study's progress to date, and asks for your feedback along the way.

Share your Feedback

Proporcionar sus comentarios

使用此表格提供您的意见

 

Virtual Question & Answer Session

The project team will host a virtual public meeting for the recommended preferred alternative on October 25, 2022 from 7:00pm to 8:0pm. The project team answered questions about the study's progress, and about the engagement materials that are part of this public comment period.

Learn More and Join the Meeting

 

Submit Comments by Email

You can submit your input about the study and its progress so far via email at any time by emailing your comments to info@cc2dca.us

Key Engagement Resources

Pre-Recorded Presentation

The project team prepared a set of pre-recorded presentations to update you on our progress and walk you through how we got to where we are today. You can watch the entire presentation (approximately 30min) or watch segments covering each part of the engagement. These videos provide the information that forms the basis for this public engagement opportunity.

Entire Video

CC2DCA Study Fall 2022 Update: Complete Pre-recorded Presentation

Actualización del estudio CC2DCA: Presentación pregrabada completa 

CC2DCA研究的最新进展:预先录制的演示文稿

Segments

 

Alternatives Brochure

Download this document for a description of the Alternatives and the Recommended Preferred Alternative.

Alternatives Brochure(PDF, 2MB)

Descargue este documento para obtener una descripción de las Alternativas y la Alternativa preferida recomendada

Folleto de alternativas(PDF, 2MB)

下载此文档以了解替代方案和推荐的首选替代方案的说明

反馈表 (PDF, 2MB)

 
Spring 2022 Newsletter

CC2DCA Study - English(PDF, 474KB) | Estudio CC2DCA - español(PDF, 464KB) | CC2DCA研究-2021年秋季简报(PDF, 548KB)

 

Winter 2021 Engagement and Community Outreach

In November 2021, the project team kicked off the 2nd public engagement checkpoint for the CC2DCA Study, covering the process from Purpose & Need to preliminary feasibility for project corridors and initial concept designs. This public engagement window was open from November 29, 2021 to January 9, 2022. For more details on this engagement effort, including how we got here, review the materials below.

Staff received your feedback in one of three ways:

Online Feedback Form

The online feedback form guided participants through a high-level overview of the study's progress to date, and asked for your feedback along the way. Here's a summary what we heard in the feedback form:

 

Virtual Question & Answer Session

The project team hosted a virtual Question & Answer session on December 7, 2021 from 7:00pm to 8:00pm. The project team answered questions about the study's progress, and about the engagement materials that are part of this public comment period.

Watch the recording | Transcript(PDF, 1MB)

Mira la Grabación | Transcripción

观看录像 | 文字记录

Submit Comments by Email

No submissions were received to the info@cc2dca.us email address for this engagement period.

Key Engagement Resources

Pre-Recorded Presentation

The project team prepared a set of pre-recorded presentations to update you on our progress and walk you through the process so far. You can watch the entire presentation (approximately 30min) or watch segments covering each part of the engagement. These videos formed the basis for this public engagement opportunity.

Entire Video

CC2DCA Study Update: Complete Pre-recorded Presentation

Actualización del estudio CC2DCA: Presentación pregrabada completa 

CC2DCA研究的最新进展:预先录制的演示文稿

Segments

Corridor Factsheets

Learn more about each of the 14 corridors analyzed and screened for the study in this set of 1-page factsheets.

Corridor Factsheets | Hojas informativas de los corridores | 通道详情介绍

VIDEO: Screening the Potential Corridors (En Español用中文)

Concepts Factsheets

Learn more about each of the initial concepts for the multi-modal connection analyzed and screened for the study in this set of 1-page factsheets

Concepts Factsheets | Hojas informativas de los conceptos | 概念设计详情介绍

VIDEO:  Screening the Potential Concepts (En Español用中文)  

Fall 2021 Newsletter

CC2DCA Study - English(PDF, 467KB)Estudio CC2DCA - español(PDF, 698KB)CC2DCA研究-2021年秋季简报(PDF, 667KB)

July 2021 Community Meeting

A virtual community meeting was held on July 15, 2021, to present the study to the public and solicit initial comments on the potential CC2DCA connection.

Online questionnaire

An online form was available from July 15 to Aug. 15, 2021, for providing input to help define the project’s purpose and need.

To receive notification of upcoming public participation opportunities, sign up for the Crystal City Pentagon City Transportation Update email on the right side of this page. 

About the Project

In 2010, Arlington County adopted the Crystal City Multimodal Transportation Study. The study made transportation improvement recommendations for the Crystal City area including the construction of a pedestrian and bicycle connection to the airport.

The Crystal City Business Improvement District (now known as the National Landing BID) initiated a feasibility assessment in 2017 that looked at how to connect Crystal City and its myriad transportation options to the airport. The study evaluated various alignment and facility types to serve existing development and planned growth in Crystal City.

During development of its FY 2019-2028 Capital Improvement Plan, the County created a new project in the Crystal City, Pentagon City, Potomac Yard Streets Program to continue alternatives analysis and preliminary planning for a connection between Crystal City and DCA. The project had limited funding due to budget constraints.

In late 2018, with the announcement of an agreement to bring Amazon’s HQ2 to Crystal City, the Commonwealth of Virginia identified a CC2DCA connection as one of five transportation projects to be fully or partially funded by the Commonwealth.

VDOT added the project to its Six-Year Improvement Program in 2019. This included an allocation of $9.5 million in federal funding for project planning, NEPA documentation and preliminary engineering.

The Federal Highway Administration (FHWA) is the lead agency for the environmental review on this project, while VDOT is the joint lead agency for the purposes of preparing the NEPA document. Concurring, cooperating, and participating agencies will be identified and formally invited in these roles after the NEPA process kicks off. To date, the National Park Service, Federal Aviation Administration, Metropolitan Washington Airports Authority, US Army Corps of Engineers, and the US Environmental Protection Agency have agreed to participate in the study as potential concurring and cooperating agencies.

At its December 2019 meeting, the County Board approved an agreement with VDOT to allow the County to administer the project’s planning, environmental review and preliminary engineering phases.

On June 30, 2020, the County advertised a request for proposals to select a consultant to complete the project’s environmental documentation and conceptual design. The County Board approved a professional services contract at its March 20, 2021, meeting.