N Ohio Street/John Marshall Trail

Location

22nd Street North, Arlington, VA 22205  View Map

Google Map

Status

Complete

N-Ohio-Street-John-Marshall-Trail-Completed_1.jpg

Location

22nd Street North to Washington Boulevard (Highland Park-Overlee Knolls Neighborhood)

Status

Complete

The North Ohio/John Marshall Trail Project is substantially complete. Please see image gallery to the right for after photos.

Construction Update, June 18, 2018

  • There is one change order for the project to repair existing sidewalk at 2 locations (one on N Ohio St close to Washington Blvd., and one on 20th St. N at a storm inlet structure adjacent to house #1920). Dates for when the contractor will perform this change order work are not yet set.
  • Construction is nearing completion, with the contractor addressing minor deficiencies.

About the Project

  • Pedestrian safety and beautification improvements along N Ohio Street and the adjacent greenbelt/John Marshall Trail.
  • Minimal disturbance to the John Marshall Trail, with County DES and DPR land ownership.
  • Some existing declining tree replacement and enhancement, as determined by County DPR and NC staff Landscape Architect, Forester and Park Area Manager.
  • Sidewalk, access path, trail and stormwater drainage facility improvements at the 20th Street N and 21st Street N intersections, and elsewhere within the project limits.
  • Existing DVP-owned Colonial and Cobra streetlights to be replaced with LED Carlyle-style streetlights.
  • Signage and striping improvements as needed.
  • Other beautification and disability access improvements within the project limits.
  • Asphalt street milling and paving, including some full depth pavement replacement, where needed.

 

Final Design Meeting Flyer

Final Design Presentation Agenda

Final Design