23rd Street South

Location

23rd Street South, Arlington, VA 22202  View Map

Google Map

Status

Complete

A-Section-of-23rd-Street-South.jpg

Location

23rd Street South from South Nash Street to Army Navy Drive (Arlington Ridge Neighborhood)

Status

Complete

Construction Update, August 17, 2018:

  • 13 of 14 driveways complete
  • Sidewalk, curb, and gutter work has been initiated
  • Drainage structures and concrete work for ADA accessible ramps and sidewalks to be completed
  • Final driveway will be completed once all drainage structures are complete

The 23rd St. S Project started construction in May, 2018 and is expected to be completed by the end of December, 2018.

Construction Hours will be from 8:00 am to 5:00 pm, Monday-Friday. Residents should expect to see contractors on-site prior to 8 am setting up for the day.

Construction Update, November 20, 2018:

  • All driveways complete
  • Drainage structures and concrete work for ADA accessible ramps and sidewalks complete
  • Sidewalk, curb, and gutter work nearing completion
  • Full depth asphalt operations in process
  • Construction is expected to be completed by the end of December 2018

Construction Update, December 2018 update:

All major construction (sidewalk, curb, and gutter, asphalt, and landscaping) was completed in December 2018.

About the Project

  • North side of the street: 5′-0″ wide concrete sidewalk adjacent to a 2′-6″ utility (grass) strip, with ADA compliant pedestrian ramps.
  • South side of the street: ADA complaint curb ramps installed at the intersection with S. Queen St. and at the corner with Army Navy Dr.  No other improvements to this side of the street.
  • Asphalt street reconstruction and pavement milling/paving.
  • The roadway will be narrowed to 34’, and will maintain two travel lanes, one in each direction.
  • On street parking will be retained on both sides, except where prohibited for traffic engineering ordinance reasons.