DEPARTMENT OF PUBLIC WORKS
ENGINEERING DIVISION

PROGRAM MISSION: The Engineering Division's mission is to provide quality transportation and utility survey, drafting, design and construction management/inspection of all non-facility capital projects.

  • The Design Sectionprovides the professional and technical expertise to prepare preliminary engineering analyses and final designs for County transportation, streetscape, and utility system projects. The Survey Section conducts field surveys and produces base map sheets with topographic information essential for the preparation of plans and designs for public improvement packages. Construction Management follows through with management and inspection of all street, bridge, and utility construction within the County right-of-way performed by private developers, utility companies, and County contractors.
  • The Customer Service Section serves as a central reception and processing point for right-of-way, building, plumbing, and demolition permit inquiries, fee collections, and media reproduction. It also manages the Utility Underground, and Utility Marking.
  • The Mapping Center serves as the Countywide base mapping and analysis section providing project tracking and management, cartographic expertise, aerial photo analysis, data maintenance, and digitizing support for all County agencies. This unit also is responsible for Geographic Information System (GIS), network administration and system analysis, database design, database administration, and GIS application development.
Engineering Division Programs
FY 2002 FY 2003 FY 2004 % Change:
Actual Adopted Proposed '03 to '04
Personnel $2,657,658 $2,783,830 $3,013,517 8%
Non-Personnel 780,292 490,105 544,169 11%
Intra-County Charges (236,676) (294,253) (307,576) 5%
Total Expenditures 3,201,274 2,979,682 3,250,110 9%
Revenues 378,579 210,000 479,000 128%
Net Tax Support $2,770,807 $2,769,682 $2,771,110 -
Authorized FTEs 68.8 69.8 71.8
Funded FTEs 68.8 69.8 71.8

SIGNIFICANT BUDGET HIGHLIGHTS:

  • One FTE was added to the Engineering Division to complete staffing needed to operate the Real Estate unit. The responsibility for all right-of-way negotiations and purchase was transferred from OSS to improve project coordination. Two FTEs were added to implement remaining parts of the Virginia Erosion/Sediment Control Act, the Chesapeake Bay Preservation Act, the County's municipal stormwater permit and the Chesapeake Bay Agreement approved by the Board. Fees were increased in FY 20002 to fund inspections and plan review positions. A portion of this additional revenue was not reflected in the FY 2003 budget. The non-personnel budget increased by $17,172 for operating expenses.
  • One position (1.0 FTE) was transferred from the Engineering Division to the Water, Sewer, and Streets Division (WSS) along with responsibility for the Paving Program. This move placed responsibility for all asphalt maintenance in one unit. It is expected this will reduce coordination issues and improve service development.
  • The principle non-personnel increases are for the addition of Chesapeake Bay staff ($17,172) and County vehicle rental rates ($15,753). The balance of the increase ($21,139) is a combination of phone charges, software maintenance costs and technology equipment upgrades.
  • A new fee will be proposed that is intended to provide funding for a position that would manage easements and encroachments. Specifics of the fee are under development and will be available in early February. As the County continues to develop, management of the scarce space grows in importance. The fee is intended to cover a substantial proportion of the direct cost of the work that will be performed. Additional staff will need to be considered if the workload warrants it.

PERFORMANCE MEASURES:

FY 2001
Actual
FY 2002
Actual
FY 2003
Estimate
FY 2004
Estimate
FY 2004
Target
Mission Outcome Measures
Projects designed within schedule and budget 23 24 45 53 59
Percent of projects designed within budget N/A N/A N/A 80% 90%
Projects built within schedule and budget 44 55 58 68 72
Percent of GIS work requests meeting customer target dates 70% 75% 78% 80% 80%

Objective: To serve the County's engineering design, survey and construction management requirements, applying resources to the management of the Capital and General Fund programs to maximize the number of projects progressing to completion.

FY 2001
Actual
FY 2002
Actual
FY 2003
Estimate
FY 2004
Estimate
FY 2004
Target
Efficiency and Workload Measures
Value of projects designed $9.2m $12.0m $8.3m $8.5m $8.5m
Miles of underground utilities designed (storm sewer, water, and sanitary sewer) 4.9 5.2 3.5 5.0 5.0
Miles of engineering field surveys completed 29.8 30.0 30.0 32.4 32.4
Acres of topographic maps produced 23.3 24.0 20.0 21.2 21.2
Linear feet of new sidewalk, curb and gutter inspected (public and private) 60,046 69,400 70,000 70,000 70,000
Building, plumbing and demolition permits reviewed 61,709 43,559 40,000 40,000 40,000
Public right-of-way permits issued 688 866 900 900 900
Number of GIS data layers maintained 19 26 32 37 37
  • Unusually large developer projects in FY 2002 affected the total linear feet of new sidewalk curb and gutter inspected. This level of developer activity is expected to continue for several years.
  • GIS data layers refers to groups of features entered into the database that are meant to be displayed as a group (e.g. buildings, water system, sanitary sewer system). Each system is mapped separately so that multiple combinations of features can be displayed on a map.

FUTURE BUDGET CONSIDERATIONS:

  • Engineering staff levels have remained static for many years while capital funds and expectations for faster project completion have increased. Although the Division reengineers its operations to try to better meet demand, capacity to deliver projects in a fair length of time continues to suffer. Increasing capacity of the Engineering staff may require more resources.