Capital Improvement Projects |
|
 |
Complete Arterial Streets |
| |
Clarendon Circle Improvements |
| |
This is a two phase design project. Phase I: Prepare Concept Desgins. Concepts to be prepared for staff analysis, and public comment. Phase II Engineering Design. Prepare Engineering Design Plans that include intersection geometry improvements, ... |
 |
Complete Arterial Streets |
| |
Clarendon Curb Extensions |
| |
Provide ADA compliant ramps on the NE, NW and South ( Central Park Plaza) side of the intersection.
Improve visibility of pedestrians crossing Wilson and Hudson Street by providing curb extensions. The curb extension on the south side of the ... |
 |
Neighborhood Conservation |
| |
N Barton Street - Part II - Fairfax Dr. to Clarendon Blvd. |
| |
PART II: Install planted corner nubs and thermoplastic crosswalk at Barton/Clarendon intersection. Install thermoplastic crosswalks across N. Barton Street at the intersection of N. 14th Street. Street improvements from Clarendon to Fairfax to ... |
 |
Park Enhancement Grants |
| |
Danville/Clarendon |
| |
New Urban Kiosk |
 |
Traffic Signals |
| |
Clarendon Area Signals |
| |
This project involves the installation of full traffic and pedestrian signals in the Clarendon area. |
 |
Transit |
| |
Clarendon Metro Station Plaza Improvements |
| |
Design and construction of pedestrian related plaza and streetscape improvements associated with the Clarendon Metrorail access points. Project will create an updated urban plaza to accommodate higher volumes of pedestrians and associated plaza ... |
 |
WALKArlington |
| |
Clarendon Blvd. at Courthouse Plaza Porkchop |
| |
Eliminate Clarendon Blvd. to 15th St. N. slip lane by incorporating island into Courthouse Plaza sidewalk & pedestrian space. (Extend driveway entrance/exit to existing Clarendon Blvd.) Reconfigure SW corner of Clarendon 15th St. intersection to ... |
|